Investment activity

Project name

Project status

Implementation years

Future projects

1

Rehabilitation of 220–500 kV OHL branches in Akmolinskiye MES branch, Vostochnye MES branch, Severnye MES branch and Tsentralnye MES branch of KEGOC, Stage II

Future

2019 - 2028

2

Rehabilitation of 220–500 kV OHL branches in Almatinskiye MES branch, Tsentralnye MES branch, and Yuzhnye MES branch of KEGOC, Stage III

Future

2021 - 2031

3

West Kazakhstan Power System and Kazakhstan Unified Power System Interconnection

Future

2021 - n/a

4

South Kazakhstan Electricity Transmission Reinforcement Project

Future

2021-2027

5

Construction of a North-South HVDC line

Future

2019-2028

6

Karaganda Electricity Transmission Reinforcement Project Construction of power grid facilities

Future

n/a

7

External power supply of the industrial zone of the city of Ekibastuz. Construction of power grid facilities

Future

n/a

Ongoing projects

1

Rehabilitation of 220-500 kV OHTLs in Aktyubinskiye MES branch, Zapadnye MES branch and Sarbaiskiye MES branch of KEGOC, Phase I

In progress

2018-2023

2

West Kazakhstan Electricity Transmission Reinforcement Project Construction of power grid facilities

In progress

2018-2024

Completed projects

1

Construction of 500 kV Second Transmission Line of Kazakhstan North-South Transit

Completed

2004-2009

2

Kazakhstan Electricity Transmission Rehabilitation Project, stage I

Completed

2000-2009

3

Alma Electricity Transmission Project

Completed

2009-2014

4

Moinak Electricity Transmission Project

Completed

2010-2012

5

Ossakarovka Transmission Rehabilitation Project

Completed

2010-2014

 6

Construction of 500 kV Ekibastuz – Shulbinsk HPP – Ust-Kamenogorsk transmission line

Completed

2011-2017

7

Construction of 500 kV North-South-East transmission line Construction of 500 kV Shulbinsk HPP - Aktogai - Taldykorgan - Alma transmission line

Completed

2012-2018

8

Pavlodar Electricity Transmission Reinforcement, Construction of a 220 kV Promyshlennaya SS - EEC transmission line, extension of 220 kV switchyards at 110 kV Pavlodarskaya and 110 kV Promyshlennaya substations

Completed

 

2010-2019

9

Kazakhstan Electricity Transmission Rehabilitation Project, phase 2

Completed

2010-2019

10

Turkestan External Power Supply Reinforcement Project Construction of power grid facilities

Completed

2019-2022


Ongoing projects:

Rehabilitation of 220– 500 kV OHTLs at in Aktyubinskiye MES branch, Zapadnye MES branch and Sarbaiskiye MES branch of KEGOC,

Rehabilitation of 220-500 kV OHTLs in KEGOC’s branches, stage I

Rehabilitation of 220-500 kV OHTL includes three stages of rehabilitation of 220-500 kV OHTL, each of which covers 3 KEGOC’s MES branches.

Project goal: improve the reliability of the NPG of Kazakhstan through the rehabilitation of the existing power lines that have surpassed the standard service life limit including the lines that will do so in the coming years.

Project implementation period: 2018-2023

Project cost: KZT 49.497 billion inclusive of VAT.

Planned financing: KZT 34.507 billion of borrowing funds, KZT 14.990 billion of the company's equity funds

Place of implementation: West Kazakhstan, Aktobe and Kostanay Oblasts of Kazakhstan.

Project description: The rehabilitation objects: 24 OHTLs of 220-500 kV, located in Aktyubinskiye MES (6 lines of 220 kV), Zapadnye MES (1 line of 220-500 kV) and Sarbaiskiye MES (17 lines of 220 kV). The length of the rehabilitated 220-500 kV overhead lines is 2,023 km. 

Current status: The feasibility study (FS) was developed and approved by GosExpertiza (opinion No. 04-0076/18 dated 21 May 2018).

The management board of KEGOC approved the key parameters of the project (Minutes No. 24 dated 10 October 2018). The board of directors of KEGOC approved the technical parameters and performance indicators of the project for “Rehabilitation of 220-500 kV OHTLs in Aktyubinskiye MES, Sarbaiskiye MES, and Zapadnye MES branches’, and approved the transition of the project to the “Definition” and “Implementation” stages (Minutes No. 2 dated 28 February 2019).

The contracts for packaged work were concluded in 2019, including turnkey construction:

1) No. 01-25-D-620 dated 19.08.2019 for "Rehabilitation of 220 kV overhead lines of Sarbayskiye MES and Zapadnye MES branches of KEGOC” with Promstroy-Energo LLP;

2) No. 01-25-D-617 dated 19.08.2019 for "Rehabilitation of 500 kV overhead lines of Sarbaiskiye MES branch of KEGOC” with ASPMK-519 LLP;

3) No. 01-25-D-618 dated 19.08.2019 for "Rehabilitation of 220 kV overhead lines of Aktyubinskiye MES and Zapadnye MES branches of KEGOC” with KarElektroSpetsStroy LLP;

In 2020 the design and estimate documentation was developed for all 24 overhead line rehabilitation facilities and respective positive expert opinions were obtained.

Construction has been in progress since 2021. Since the beginning of the project, construction work has been carried out at 22 out of 24 power transmission lines (including construction work completed at 18 overhead lines, of which 16 overhead lines have been put into operation and 2 overhead lines are at the stage of acceptance into operation). Work continues on the remaining 6 overhead lines. Since the beginning of the project, 1,767 km of the 2,023 km of overhead lines have been rehabilitated (or 87.3% of the total length of the rehabilitated lines), including 460.29 km completed in 2022. 

     

West Kazakhstan Electricity Transmission Reinforcement Project. Construction of Power Grid Facilities

Project goal: Improve network capacity and reliability of electricity supply to consumers in the Western zone of Kazakhstan UPS by re-enforcing 220 kV electrical links between West regions of Kazakhstan.

Project implementation period: 2018-2023

Project cost: KZT 54.138 billion inclusive of VAT.

Planned financing: KZT 34.865 billion from loans, KZT 19.273 billion from Company's equity funds

Location: West Kazakhstan and Atyrau Oblasts of Kazakhstan

Project description: The project suggests construction of the second circuit of the existing of 220 kV Uralskaya - Pravoberezhnaya - Inder - Karabatan - Kulsary - Tengiz electricity transmission lines including connection to the existing 220 kV substations and to new Karabatan power distribution station and includes the following facilities:

1) rehabilitation of 220 kV Uralskaya SS;

2) extension of 220 kV OSG at 220 kV Pravoberezhnaya SS;

3) extension of 220 kV OSG including 2 units of 220 kV controlled shunt reactors at 220 kV Inder SS;

4) extension of 220 kV Kulsary SS;

5) extension of 220 kV Tengiz SS;

6) construction of 220 kV Karabatan power distribution station;

7) construction of 220 kV Uralskaya - Pravoberezhnaya transmission line;

8) construction of 220 kV Pravoberezhnaya - Inder transmission line;

9) construction of 220 kV Inder - Karabatan transmission line;

10) construction of 220 kV Karabatan - Kulsary transmission line;

11) construction of 220 kV Kulsary - Tengiz transmission line.

Current status: The feasibility study (FS) report for the project was developed in 2019 and approved by GosExpertiza (report No. 01-0006/19 dated 04 January 2019). The board of directors of KEGOC approved project performance indicators specified in the feasibility study report (Minutes No. 2 dated 28 February 2019).

In 2019, 11 contracts were concluded for design and survey of overhead transmission lines and substations with design institutes: Eshimkulov N.T. individual entrepreneur; MangistauEnergoMontazhNaladka LLP; SIT-Stroy LLP.

In 2021, for all 11 facilities, including 6 substations (220 kV Uralskaya, Pravoberezhnaya, Inder, Karabatan, Tengiz, and Kulsary substations) and 5 lines (220 kV Uralskaya - Pravoberezhnaya, Pravoberezhnaya - Inder, Karabatan - Kulsary, Inder - Karabatan, Kulsary - Tengiz) procurements for construction and installation works were completed through open tenders in accordance with the the Procurement Management Standard of Samruk-Kazyna Sovereign Wealth Fund JSC and organizations, fifty or more percent of voting shares (participatory interests) of which are directly or indirectly owned by Samruk-Kazyna on the right of ownership or trust management, approved by the Decision of the Board of Samruk-Kazyna (minutes No. 31/19 dated 9 September 2019 ) and the following contracts have been concluded:

1. Rehabilitation of 220 kV Uralskaya SS, ASPMK LLP (PI No. 541278-487189 dated 11 March 2021), contract No. 541278/2021/1/01-25-D-206 dated 25 March 2021;

2. Expansion of 220 kV outdoor switchgear at 220 kV Pravoberezhnaya SS, KarElektroSpetsStroy LLP (PI No. 541280-487196 dated 11 March 2021), contract No. 541280/2021/1/01-25-D-203 dated 19 March 2021;

3. Expansion of 220 kV outdoor switchgear at including installation of 2 pcs of 220 kV CSRs at 220 kV Inder SS, ASPMK LLP (PI No. 5414443-487619 of 11 March 2021), contract No. 541443/2021/1/01-25-D-216 dated 29 March 2021;

4. Expansion of 220 kV Kulsary SS, KarElektroSpetsStroy LLP (PI No. 541326-487353 dated 11 March 2021), contract No. 541326/2021/1/01-25-D-207 dated 25 March 2021;

5. Extension of 220 kV Tengiz SS, ASPMK LLP (PI No. 541444-487176 dated 11 March 2021), contract No. 541444/2021/1/01-25-D-205 dated 25 March 2021;

6. Rehabilitation of 220 kV Karabatan SS, EIS Corporation LLP (PI No. 572741-538677 dated 21 May 2021), contract No. 572741/2021/1/01-25-D-440 dated 11 June 2021;

7. Construction of a single-circuit 220 kV Uralskaya - Pravoberezhnaya overhead line in the West Kazakhstan region, ASPMK-519 LLP (PI No. 541310-487170 of 11 March 2021), contract 541310/2021/1/01-25-D-204 dated 25 March 2021;

8. Construction of a single-circuit 220 kV Pravoberezhnaya - Inder overhead line in the West Kazakhstan and Atyrau regions, KarElektroSpetsStroy LLP (PI No. 541282-488426 of 12 March 2021), contract No. 541282/2021/1/01-25-D-211 dated 26 March 2021;

9. Construction of a single-circuit 220 kV Inder - Karabatan overhead line in Atyrau region, ASPMK-519 LLP, (PI No. 548874-499507 dated 30 March 2021), contract No. 548874/2021/1/01-25-D-279 dated 08 April 2021;

10. Construction of a single-circuit 220 kV Karabatan - Kulsary overhead line, KarElektroSpetsStroy LLP (PI No. 548898-495461 of 25 March 2021), contract No. 548898/2021/1/01-25-D-230 of 01 April 2021;

11. Construction of a single-circuit 220 kV Kulsary - Tengiz overhead line, PromStroy-Energo LLP (PI No. 553462-501363 of 02 April 2021), contract No. 553462/2021/1/01-25-D-284 dated 9 April 2021.

Also in 2021, design and estimate documentation was developed for all 11 facilities (6 substations and 5 overhead lines), positive opinions were received from the examination authority for the design and estimate documentation, and construction and installation work began.

Currently, construction and installation work is being carried out at all five sections of the 220 kV Uralskaya - Pravoberezhnaya - Inder - Karabatan - Kulsary - Tengiz overhead lines and at 220 kV Uralskaya, Pravoberezhnaya, Inder, Kulsary, Tengiz substations and Karabatan 220 kV distribution substation. In total, since the beginning of the project, 297.8 of 779.7 km of conductor have been installed (or 38.1% of the total length of the transmission lines), including 244.4 km completed in 2022. In total, 2,898 of 4,182 transmission towers have been installed (or 69.2% of the total number of towers, including 1,760 towers in 2022).

 

Turkestan External Power Supply Reinforcement Project.

Construction of Power Grid Facilities

Project goal: increase reliability of power supply to the Turkestan energy region.

Project implementation period: 2019-2022

Project cost: KZT 7.63 billion inclusive of VAT.

Estimated project financing: equity funds.

Location: Turkestan oblast.

Project description: construction of the new 220 kV substation in the Turkestan region, which will be connected to the existing 220 kV network. The new 220 kV substation will be an additional power supply centre for the Turkestan energy region. It will facilitate development of the local electrical distribution network, and provide necessary network capacity.

The project shall cover the projected significant increase in electricity consumption in the Turkestan energy region.

Current status: The feasibility study (FS) report was developed and approved by GosExpertiza (opinion report No. 01-0489/19 dated 28 November 2019).

In 2020 contract No. 442101/2020/1 dated 14 July 2020 was concluded with ASPMK-519 LLP on a turnkey basis, which includes the development of design estimates, the supply of certain types of equipment and the performance of construction and installation works, Also, contracts were concluded for the supply of 220/110/10 kV autotransformers, 110-220 kV SF6 circuit breakers, 110-220 kV disconnectors, 110-220 kV voltage transformers, 110-220 kV current transformers and 110 kV-220 kV surge arresters and 110-220 kV bus supports.

In 2021 the development of design and estimate documentation for the rehabilitation of 220 kV L-2439 GNPS-Kentau overhead transmission line, 220 kV L-2309 GNPS-Shymkent overhead transmission line and construction of 220 kV Ortalyk substation has been completed, an approval of project examination authority and permits has been received for construction and installation works. (No. CEQZ-0223/21 of 13 August 2021, No. RT-0023/21 of 01 September 2021 and No. 01-0708/21 of 29 December 2021)


In 2022, all construction and erection works and pre-commissioning works were completed: A new 220 kV Ortalyk substation was built near the city of Turkestan. It was put into operation. The commissioning acceptance certificate was approved by the Chairman of the Management Board, order No. 227 dated 28 October 2022. 

Future projects


Rehabilitation of 220–500 kV OHL branches in Akmolinskiye MES branch, Vostochnye MES branch, Severnye MES branch and Tsentralnye MES branch of KEGOC, Stage II

The project goal:

Improve the reliability of the NPG of Kazakhstan through the rehabilitation of the existing power lines that have surpassed the standard service life limit including the lines that will do so in the coming years.

Rehabilitation of 220–500 kV OHL branches in Akmolinskiye MES branch, Vostochnye MES branch, Severnye MES branch and Tsentralnye MES branch of KEGOC, Stage II covers 48 overhead lines of 220-500 kV in the respective branches with the total length of about 4200 km.

Project implementation period: 2019-2028

Project cost: KZT 95.22 billion inclusive of VAT

Planned financing: KZT 63.09 billion of borrowing funds, KZT 32.13 billion of the company's equity funds

Place of implementation: territory of the Republic of Kazakhstan.

Current status:

In 2019 a contract has been signed for a feasibility study. A complete examination of 48 overhead lines has been completed. Currently, work is underway to prepare and approve overhead line technical survey reports and the develop a feasibility study report.

Rehabilitation of 220–500 kV OHL branches in Almatinskiye MES branch, Tsentralnye MES branch, and Yuzhnye MES branch of KEGOC, Stage III

The project goal:

Improve reliability of the NPG of Kazakhstan through the rehabilitation of the existing power lines to extend the service life by at least 30 years.

Stage III of the project includes rehabilitation of 44 lines of 220-500 kV lines in the respective branches with the total length of about 4300 km.

Project implementation period: 2021-2031

Project cost: KZT 96.06 billion inclusive of VAT

Planned financing: KZT 66.99 billion of borrowing funds, KZT 29.07 billion of the company's equity funds

Place of implementation: territory of the Republic of Kazakhstan.

Current status:

In 2021 a contract has been signed for a feasibility study. The contractor is conducting a survey of overhead lines.

The deadline for the completion of the feasibility study is 2023.

External power supply to the industrial area of Ekibastuz Construction of power grid facilities

The project objective:

Ensure reliable power supply of the Industrial zone of Ekibastuz and consumers of Ekibastuz energy hub

Project implementation period: 2020 - 2026

Project cost: KZT 18.11 billion inclusive of VAT.

Planned financing: KZT 12.48 billion from loans, KZT 5.63 billion from Company's equity funds

Place of implementation: territory of the Republic of Kazakhstan.

Current status:

Contract has been signed for development of feasibility study.

The contractor is conducting a feasibility study. 

West Kazakhstan Power System and Kazakhstan Unified Power System Interconnection Project

The project goal:

Interconnect Zone West with the main part of the UPS of Kazakhstan over Kazakhstan inland territory to ensure energy security and energy independence of the Western regions of Kazakhstan, improve the reliability of power supply to consumers in Zone West.

Current status:

 The preliminary FS study confirmed the advisability of interconnecting of the energy system of Western Kazakhstan with the UPS of Kazakhstan.

Procurement procedures are being carried out to determine the contractor for the feasibility study. 

South Kazakhstan Electricity Transmission Reinforcement Project

The project goal:

Strengthen the electric power system of Zone South of the UPS of Kazakhstan over the inland territory to ensure the reliability of power supply to consumers in Zone South and to strengthen its electrical interconnections.

Project cost: will be known upon completion of the feasibility study.

Project implementation period: 2021-2027

Current status:

Contract has been signed for a feasibility study. The results of the 1st stage of the feasibility study have been approved. The development of the feasibility study continues.

 

1. Joint Order on approval of KEGOC Investment Programme for 2016-2020
4. Performance indicators of the investment programme (project) in 2016
5. Information on the implementation of the investment program of KEGOC JSC for 2016
6. Performance indicators of the investment programme (project) in 2016
8. Joint Order on Amendments for 2016 Investment Programme of KEGOC
9. Joint Order on Amendments for 2016-2017 Investment Programme of KEGOC for 2016-2020
10. Information on the implementation of the investment program of KEGOC JSC for 2017
12. Performance indicators of the investment programme (project) in 2017
15. Performance indicators of the investment programme (project) in 2017
16. Joint Order on Amendments for 2017-2018 Investment Programme of KEGOC for 2016-2020
17. Information on the implementation of the investment program of KEGOC JSC for 2018
18. Joint Order on Amendments for 2019 Investment Programme of KEGOC for 2016-2020
18. Joint Order on Amendments for 2019 Investment Programme of KEGOC for 2016-2020
19. Joint Order on Amendments for 2019 Investment Programme of KEGOC for 2016-2020
20. Information on the implementation of the investment program of KEGOC JSC for 2019
21. Joint Order on Amendments for 2019 Investment Programme of KEGOC for 2016-2020
22. Information on the implementation of the investment program for 2020
23. Joint Order on approval of KEGOC Investment Programme for 2021-2025
24. Information on the implementation of the investment program of KEGOC JSC for 1 Q 2021
25. Progress of KEGOC investment projects for Q1 2021
26. Information on the implementation of the investment program of KEGOC JSC for 2 Q 2021
27. Progress of KEGOC investment projects for Q2 2021
28. Information on the implementation of the investment program of KEGOC JSC for 3 Q 2021
29. Progress of KEGOC investment projects for Q3 2021
30. Progress of KEGOC investment projects for Q4 2021
31. Progress of KEGOC investment projects for 2021
32. KEGOC's Investment Projects Progress in Q1 2022
33. Information on the implementation of the investment program for 1st half of 2022
35. KEGOC’s Investment Projects Progress in Q2 2022
36. KEGOC’s Investment Projects Progress in Q3 2022
38. Report on the implementation of the investment program for the 1st year of release

The amount of capital investments in Q3 2016 was KZT 18 419,373 million.

The KEGOC's investment program for 2014-2015, approved jointly by the Agency for Regulation of Natural Monopolies (order No.155-ОД dated 27 May 2013) and the Ministry of Industry and New Technologies (order No.256 of dated 22 August 2013) requires KZT 18,841.340 million of capital investments in 2014.

The amount of capital investments in Q1 2015 was KZT 616.491 million.

The amount of capital investments in H1 2015 was KZT 1,981.163 million.

The amount of capital investments in Q3 2015 was KZT 10 870,013 million.

The amount of capital investments in Q4 2015 was KZT 24 486,242  million.

The amount of capital investments in Q1 2014 was KZT 2,425.909 million, or 12.9% of the annual plan.

The amount of capital investments in H1 2014 was KZT 6,636.044 million, or 35.2% of the annual plan.

The amount of capital investments in Q3 2014 was KZT 12,426.527 million, or 65.9% of the annual plan.     

Updated the KEGOC's investment program for 2014 requires KZT 21,009.679 million of capital investments.

The amount of capital investments in Q4 2014 was KZT 26,264.341 million, or 125.0% of the annual plan.

The KEGOC's investment program for 2012-2013, approved jointly by the Agency for Regulation of Natural Monopolies (order No. 96-ОД dated 03 April 2013) and the Ministry of Industry and New Technologies (order No.162 of dated 27 May 2013) requires KZT 25,683.322 million of capital investments in 2012. Actual disbursement of capital investments in 2012 was KZT 24530.922 million.

The KEGOC's investment program for 2012-2013, approved jointly by the Agency for Regulation of Natural Monopolies (order No. 96-ОД dated 03 April 2013) and the Ministry of Industry and New Technologies (order No.162 of dated 27 May 2013) requires KZT 40,576.809 million of capital investments in 2013. Actual disbursement of capital investments in 2013 was KZT 42,646.668 million.

KEGOC investment program for 2011 approved jointly by the Agency for Regulation of Natural Monopolies (order No.141-ОД dated 6 May 2011) and the Ministry of Industry and New Technology (order No. 134 dated 11 May 2011) requires KZT 16,805.443 million of capital investments in 2010. Actual disbursement of capital investments in 2011 was KZT 18,232.876 million. 

KEGOC investment program for 2010 approved jointly by the Agency for Regulation of Natural Monopolies (order No.91-ОД dated 19 March 2010) and the Ministry of Industry and New Technologies (order No.26 dated 15 April 2010).

KEGOC investment program approved jointly by the Agency for Regulation of Natural Monopolies (order No.91-ОД dated 19 March 2010) and the Ministry of Industry and New Technology (order No. 26 dated 15 April 2010) requires for KZT 6307.390 million of capital investments in 2010. Actual disbursement of capital investments in 2010 was KZT 8,093.566 million.

Hotline

Feedback