KEGOC informs about full restoration of power supply to Zone South of Kazakhstan UPS.
To date, the normal operation of the national power grid has been fully restored including parallel operation with the power systems of Kyrgyzstan and Uzbekistan.
At 15:50 (Nur-Sultan time), all load-shedding affected consumers in Almaty city, Almaty, Turkestan, Kyzylorda, and Zhambyl oblasts were fully reconnected, except for Kazphosphat LLP and TMP LLP.
At 20:41, all load-shedding affected consumers in Zone South, including Zhambyl oblast, were reconnected. The unified power system of Kazakhstan operates normally.
KEGOC JSC